The Revival of JP Sports City: How YEIDA is Stepping in to Save 4,500 Homebuyers

YEIDA is taking over 4,500+ incomplete flats in JP Sports City after a ₹3,621 crore default by JAL. A "Zero Period" waiver protects buyers from interest and penalties for the 2020–2024 delay period.

The long-standing saga of JP Sports City in Greater Noida has entered a definitive new chapter. For over 14 years, nearly 4,638 homebuyers have been left in a state of financial and emotional limbo. However, following a decisive intervention by the Allahabad High Court, the Yamuna Expressway Industrial Development Authority (YEIDA) has officially assumed the responsibility of completing the stalled residential projects. This move marks one of the most significant state-led interventions in the Indian real estate sector, aimed at protecting middle-class investors from the fallout of corporate insolvency.

The crisis began when the original developer, Jaiprakash Associates Limited (JAL), failed to meet its financial obligations to the state. By 2020, the developer had accumulated dues totaling approximately ₹3,621 crore. Consequently, YEIDA cancelled the allotment of the 1,000-hectare Special Development Zone land. Although the developer challenged this in court, the Allahabad High Court upheld the cancellation in March 2025, noting the developer’s consistent failure to pay despite receiving 28 separate notices over the years.

To facilitate the takeover, YEIDA has commissioned a thorough technical and financial audit by the global consultancy firm Currie & Brown. This audit is a critical step because the project is burdened with over ₹2,100 crore in outstanding bank loans. The firm is currently mapping out the status of every single unit—identifying which are sold, which are unsold, and exactly how much capital is required to finish the remaining construction. This data will form the basis of a Request for Proposal to select new builders under an Engineering, Procurement, and Construction model.

One of the most significant victories for the buyers is the implementation of the "Zero Period" policy. The court has mandated that the period from February 11, 2020, to March 2024 be treated as a zero period. This means that homebuyers will not be charged any interest, late fees, or penalties for the duration that the project was legally stalled. This relief is expected to save individual owners lakhs of rupees in unnecessary financial burdens.

However, the path forward is not without risks. The Jaypee Group has moved the Supreme Court to challenge the High Court's ruling. While there is currently no stay order preventing YEIDA from working, the final outcome of this litigation remains a factor. Furthermore, the audit has highlighted that JAL used the project land to secure massive loans, creating a complex financial web that YEIDA must untangle to ensure the new construction is safely funded.

The state government has formed a high-level monitoring committee to oversee this transition. Chaired by the Principal Secretary of Industrial Development, the committee includes the CEO of YEIDA and representatives from UP-RERA. Their goal is to ensure a transparent process as YEIDA moves toward a three-year completion timeline, with a target of finishing 75 percent of the work within the first 12 months.

Published On:
December 15, 2025
Updated On:
December 15, 2025
Harsh Gupta

Realtor with 10+ years of experience in Noida, YEIDA and high growth NCR zones.

YoutubeInstagram